Press Release (Feb 12,2009)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of February 12th)
We are announcing the status of major inspections and restoration works and nonconformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status

 ◇ Inspection and restoration completed between February 6th to February 12th, 2009 
    (Completed on the following date) 

   - Unit No.7 Main generator inspection (Leakage confirmation tests and restoration): 
      February 7th 

 ◇ Inspection and restoration to be commenced between February 13th to February 19th, 2009 
    (To be commenced on the following date)  

   - Unit No.1 Seismic reinforcement works (Unit No.1 and Unit No.2: Preparation for 
     seismic reinforcement works for stack): 
      February 16th 
   - Unit No.2 Reactor recirculation piping preventive maintenance (Ultrasonic testing): 
      February 18th 
   - Unit No.6 Fuel-load work (Core status confirmation): 
      February 16th 
   - Unit No.6 Reactor pressure vessel closure: 
      February 18th 
   - Unit No.6 System functional test (Reactor shut-down margin inspection): 
      February 17th 
   - Unit No.6 System functional test (Selected control rod insertion inspection): 
      February 17th 

 ◇ Work Schedule of Major Inspection/Restoration from February 8th to March 7th, 2009

   - Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                           ....Appendix

 (Reference) 
   Nonconformances Found in the Inspection and Restoration Works Performed after the 
   Niigata-Chuetsu-Oki Earthquake

   Based on the "Public Announcement Regarding Nonconformance Found in the Inspection 
   and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo 
   Electric Power Company, Incorporated (TEPCO) provides this announcement containing 
   incidents information reported from February 5th to February 11th, 2009. 

 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
< Reports from February 5 to February 11, 2009 >
Reports from February 5 to February 11, 2009
◇ Other Findings * Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake; Grades As, A, B, C, D; and non-graded)
* Numbers were corrected to reflect nonconformance incidents that had been identified as not related to the Chuetsu-Oki Earthquake (4 cases).
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                                (PDF 95.7KB)