Press Release (Jan 22,2009)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of January 22nd)
We are announcing the status of major inspections and restoration works and nonconformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status

 ○ Inspection and restoration completed between January 16th to January 22nd, 2009 
    (Completed on the following date) 

   • Unit No.3 Reactor recirculation piping preventive maintenance (Ultrasonic testing): 
      January 22nd 
   • Unit No.6 Seismic reinforcement works (Seismic reinforcement works such as pipe 
     supports): 
      January 19th 

 ○ Inspection and restoration to be commenced between January 23rd to January 29th, 2009 
    (To be commenced on the following date)  

   • Unit No.1 Seismic reinforcement works (Preparation for seismic reinforcement 
     works for the fuel handling machine): 
      January 23rd 
   • Unit No.1 Seismic reinforcement works (Seismic reinforcement works for the roof 
     truss of the reactor building): 
      January 22nd* 
   • Unit No.3 Reactor recirculation piping preventive maintenance (Preparation for 
     radio frequency induction heating): 
      January 23rd 
   • Unit No.6 Control rod drive inspection (Disassembly and inspection): 
      January 26th
   • Unit No.6 System functional test (Interlock functional test of reactor protection 
     system): 
      January 23rd 
   • Relocation work of ground motion observation points (Seismometer installation work): 
      January 26th 
                                            * Work schedules added and altered this week.

 ○ Work Schedule of Major Inspection/Restoration from January 18th to February 14th, 2009

   • Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                           ....Appendix

 (Reference) 
  Nonconformances Found in the Inspection and Restoration Works Performed after the 
  Niigata-Chuetsu-Oki Earthquake

  Based on the "Public Announcement Regarding Nonconformance Found in the Inspection 
  and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo 
  Electric Power Company, Incorporated (TEPCO) provides this announcement containing 
  incidents information reported from January 15th to January 21st, 2009. 

 ○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
< Reports from January 15 to January 21, 2009 >
Reports from January 15 to January 21, 2009
○ Other Findings • Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                                (PDF 114KB)