We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
○ Inspection and restoration completed between December 26th, 2008 to January 8th, 2009
(Completed on the following date)
No notable activity during this week.
○ Inspection and restoration to be commenced between January 9th to January 15th, 2009
(To be commenced on the following date)
Unit No.3 Main exhaust duct inspection and restoration (Restoration of substruction):
January 9th
Unit No.6 Turbine inspection (Restoration work of blades of low-pressure turbine):
January 8th*
Unit No.6 System functional test (Rated capacity verification test of emergency
diesel generator (A)):
January 13th
Unit No.6 System functional test (Functional test of emergency diesel generator,
high pressure core flooder system,low pressure flooder system and reactor component
cooling water system):
January 15th
Restoration of laundry facility building on Arahama-side (Preparation work):
January 13th
* Work schedules added and altered this week.
○ Work Schedule of Major Inspection/Restoration from January 4th to January 31st, 2009
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the
Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from December 25th, 2008 to January 7th, 2009.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
< Reports from December 25, 2008 to January 7, 2009 >
○ Other Findings
Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 98.9KB)