We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
○ Inspection and restoration completed between December 12th to December 18th, 2008
(Completed on the following date)
Unit No.3 Stack inspection (Inspection of stand-by gas treatment system pipe support):
December 15th
Unit No.7 Turbine inspection (Low-pressure turbine (A) (B) (C) restoration work
of blades):
December 18th
House boilers inspection (Ohminato-side: 4C Inspection of boilers):
December 17th
○ Inspection and restoration to be commenced between December 19th to December 25th, 2008
(To be commenced on the following date)
Unit No.3 Main exhaust duct inspection and restoration (Restoration of substruction):
December 24th
Unit No.6 Stack inspection (Inspection of outdoor duct):
December 19th*
Unit No.6 System functional test (Functional test of liquid waste disposal system):
December 12th*
Unit No.6 System functional test (Functional test of primary containment vessel
isolation valve):
December 20th
Unit No.6 System functional test (Functional test of primary containment vessel
spray system):
December 25th
Unit No.7 Turbine inspection (Restoration of low-pressure turbine casing):
December 19th
On-site check, inspection and restoration of the oil protection bank for the
transformer (Unit No.4 Restoration work):
December 13th*
* Work schedules added and altered this week.
○ Work Schedule of Major Inspection/Restoration from December 14th, 2008 to January 10th, 2009
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the
Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from December 11th to December 17th, 2008.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
< Reports from December 11 to December 17, 2008 >
|
○ Other Findings
As for the low-pressure turbine (A), (B) and (C), restoration of turbine blades,
such as installation of rotor blades and cleansing of rotor etc., will be completed
on December 18th, 2008.
Subsequently, restoration of casing of the low-pressure turbine will be commenced
on December 19th, 2008 (scheduled date of completion is to be determined).
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 119KB)
|