search



Corporate Information

 
Press Release (Dec 18,2008)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of December 18th)
We are announcing the status of major inspections and restoration works and nonconformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status

 ○ Inspection and restoration completed between December 12th to December 18th, 2008 
    (Completed on the following date) 

   • Unit No.3 Stack inspection (Inspection of stand-by gas treatment system pipe support): 
      December 15th 
   • Unit No.7 Turbine inspection (Low-pressure turbine (A) (B) (C) restoration work 
     of blades): 
      December 18th 
   • House boilers inspection (Ohminato-side: 4C Inspection of boilers): 
      December 17th 

 ○ Inspection and restoration to be commenced between December 19th to December 25th, 2008 
    (To be commenced on the following date)  

   • Unit No.3 Main exhaust duct inspection and restoration (Restoration of substruction): 
      December 24th 
   • Unit No.6 Stack inspection (Inspection of outdoor duct): 
      December 19th* 
   • Unit No.6 System functional test (Functional test of liquid waste disposal system): 
      December 12th* 
   • Unit No.6 System functional test (Functional test of primary containment vessel 
     isolation valve): 
      December 20th 
   • Unit No.6 System functional test (Functional test of primary containment vessel 
     spray system): 
      December 25th 
   • Unit No.7 Turbine inspection (Restoration of low-pressure turbine casing): 
      December 19th 
   • On-site check, inspection and restoration of the oil protection bank for the 
     transformer (Unit No.4 Restoration work): 
      December 13th* 
                                             * Work schedules added and altered this week. 

 ○ Work Schedule of Major Inspection/Restoration from December 14th, 2008 to January 10th, 2009

  • Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
    Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                          ....Appendix

 (Reference) 
  Nonconformances Found in the Inspection and Restoration Works Performed after the 
  Niigata-Chuetsu-Oki Earthquake

  Based on the "Public Announcement Regarding Nonconformance Found in the Inspection 
  and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo 
  Electric Power Company, Incorporated (TEPCO) provides this announcement containing 
  incidents information reported from December 11th to December 17th, 2008. 

 ○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
< Reports from December 11 to December 17, 2008 >
Reports from December 11 to December 17, 2008
○ Other Findings • As for the low-pressure turbine (A), (B) and (C), restoration of turbine blades, such as installation of rotor blades and cleansing of rotor etc., will be completed on December 18th, 2008. Subsequently, restoration of casing of the low-pressure turbine will be commenced on December 19th, 2008 (scheduled date of completion is to be determined).
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                                (PDF 119KB)



back to page top


to TOP