search



Corporate Information

 
Press Release (Nov 13,2008)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of November 13th)
We are announcing the status of major inspections and restoration works and nonconformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status

 ○ Inspection and restoration completed between November 7th to November 13th, 2008 
    (Completed on the following date) 

   • Unit No.5 Stack inspection (Inspection of stack radiation monitor sampling pipe): 
      November 7th
   • Unit No.6 Main transformer inspection (Installation work): 
      November 11th 
   • Unit No.6 Stack inspection (Inspection of stack radiation monitor sampling pipe): 
      November 10th 
   • Unit No.7 Confirmation of the control rod drive coupling (by underwater camera): 
      November 7th
   • High-voltage start-up transformer No.3 inspection (Installation work):
      To be completed on November 13th 

 ○ Inspection and restoration to be commenced between November 14th to November 20th, 2008 
    (To be commenced on the following date) 

   • Unit No.1 Turbine inspection (High-pressure turbine and low pressure turbine (A) (B) (C) 
     detailed inspection): 
      November 17th 
   • Unit No.1 House transformer inspection (1A and 1B Transportation into the factory) : 
      November 15th 
   • Unit No.1 Main exhaust duct inspection and restoration (Ventilation system exhaust 
     stack inlet radiation monitor sampling pipe inspection): 
      November 17th 
   • Unit No.2 Excitation transformer inspection (Transportation into the factory) : 
      November 15th 
   • Unit No.3 House transformer inspection (3A and 3B Carrying in) : 
      November 17th 
   • Unit No.3 House transformer inspection (3A and 3B Installation work) : 
      November 18th 
   • Unit No.3 Excitation transformer inspection (Carrying in) : 
      November 17th 
   • Unit No.3 Excitation transformer inspection (Installation work) : 
      November 18th 
   • Unit No.5 Main exhaust duct inspection and restoration (Restoration of substruction): 
      November 20th 
   • Unit No.7 Fuel-load work (Core status confirmation): 
      November 17th 
   • Unit No.7 Reactor pressure vessel closure (closure work): 
      November 18th 
   • Unit No.7 Turbine inspection (Low pressure turbine (A) casing restoration): 
      November 15th 
   • Unit No.7 Reactor internal pump input transformer inspection (Energization for testing 
     without load): 
      November 18th 
   • Unit No.7 System functional test (Reactor shut-down margin inspection): 
      November 17th 
   • Unit No.7 System functional test (Selected control rod insertion inspection): 
      November 18th 
   • High-voltage start-up transformer No.3 inspection (Energization for testing without load):
      November 14th

 ○ Work Schedule of Major Inspection/Restoration from November 9th to December 6th, 2008

    • Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
      Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                            ....Appendix

 (Reference) 
   Nonconformances Found in the Inspection and Restoration Works Performed after the 
   Niigata-Chuetsu-Oki Earthquake

   Based on the "Public Announcement Regarding Nonconformance Found in the Inspection 
   and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo 
   Electric Power Company, Incorporated (TEPCO) provides this announcement containing 
   incidents information reported from November 6th to November 12th, 2008. 

  ○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
< Reports from November 6 to November 12, 2008 >
Reports from November 6 to November 12, 2008
○ Other Findings • Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake; Grades As, A, B, C, D; and non-graded)
* Numbers were corrected to reflect nonconformance incidents that had been identified as not related to the Chuetsu-Oki Earthquake (12 cases) and that had been double-counted (1 case). • Visual inspection was conducted for stack radiation monitor sampling pipes of Unit No.1 and Unit No.3 after removing insulation. As a result of the inspection, damage was found on an intake side pipe of sampling pump of Unit No.3, and a misalignment was found on the joint of discharge side pipes of sampling pump of Unit No.1. These incidents did not lead to any radiological impact to the environment. Additionally, visual inspection was conducted for stack radiation monitor sampling pipes of Unit No.2 and Unit No. 4 after removing insulation, and no additional damage was found. Subsequently, visual inspection was conducted for stack radiation monitor sampling pipes of Unit No.5, Unit No.6 and Unit No.7 from December 3rd to December 10th, 2008 after removing insulation, and no additional damage was found. Detailed inspection will be continued as well as root cause analysis of damages of Unit No.1 and Unit No.3.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                                (PDF 42.5KB)


back to page top


to TOP