We are announcing the status of major inspections and restoration works and
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after
the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
○ Inspection and restoration completed between August 29th to September 4th, 2008
(Completed on the following date)
• Unit No.4 House transformer inspection (4A and 4B Transportation into the factory):
August 29th
• Unit No.4 Excitation transformer inspection (Transportation into the factory):
August 29th
• On-site check, inspection and restoration of the oil protection bank for the transformer
(Unit No.7 Restoration work):
August 29th
○ Inspection and restoration to be commenced between September 5th to September 11th, 2008
(To be commenced on the following date)
• Unit No.3 Inspection of new fuel storage warehouse and new fuels in the warehouse
(Inspection of new fuel storage warehouse):
September 8th
• Unit No.3 Inspection of power supply input transformer of the primary loop recirculation
system adjustable speed drive (Transportation into the factory):
September 11th
• Unit No.5 Main generator inspection (Restoration work):
September 11th
• Unit No.6 Seismic reinforcement work (Seismic reinforcement works for the roof truss of
the reactor building):
September 3rd*
• Unit No.6 Seismic reinforcement work (Seismic reinforcement works for exhaust stack):
September 5th
• Unit No.7 Seismic reinforcement work (Seismic reinforcement works for exhaust stack):
September 5th
• High-voltage start-up transformer #3 inspection (Carrying in):
September 5th
• High-voltage start-up transformer #3 inspection (Installation work):
September 6th
• On-site check, inspection and restoration of the oil protection bank for the transformer
(Unit No.4 Preparation for restoration work):
September 2nd*
• House boilers inspection (3A Inspection):
September 9th
* Work schedules added this week.
○ Work Schedule of Major Inspection/Restoration from August 31st to September 27th, 2008
• Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the
Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from August 28th to September 3rd, 2008.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake) |
< Reports from August 28 to September 3, 2008 > |
○ Other Findings
Nothing to disclose this week. Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear