Press Release (Aug 28,2008)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of August 28th)
We are announcing the status of major inspections and restoration works and 
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after 
the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status

 ○ Inspection and restoration completed between August 22nd to August 28th, 2008 
    (Completed on the following date) 

   • Unit No.2 Main generator inspection (Rotor transportation into the factory): 
      August 22nd 
   • Unit No.4 Main transformer inspection (Transportation into the factory): 
      August 25th 
   • Unit No.4 Stack inspection (Internal inspection of stack): 
      August 25th 
   • On-site check, inspection and restoration of the oil protection bank for the 
     transformer (Unit No.1 Recovery of oil-contaminated soil)
      August 22nd 
   • House boilers inspection (2A inspection): 
      August 28th 

 ○ Inspection and restoration to be commenced between August 29th to September 4th, 2008 
    (To be commenced on the following date) 

   • Unit No.3 Inspection of new fuel storage warehouse and new fuels in the warehouse 
     (Inspection of new fuels): 
      September 2nd 
   • Unit No.4 House transformer inspection (4A and 4B Transportation into the factory): 
      August 29th 
   • Unit No.4 Excitation transformer inspection (Transportation into the factory): 
      August 29th 

 ○ Work Schedule of Major Inspection/Restoration from August 24th to September 29th, 2008

   • Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                           ....Appendix

 (Reference)
  Nonconformances Found in the Inspection and Restoration Works Performed after the 
  Niigata-Chuetsu-Oki Earthquake

  Based on the "Public Announcement Regarding Nonconformance Found in the Inspection 
  and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo 
  Electric Power Company, Incorporated (TEPCO) provides this announcement containing 
  incidents information reported from August 21st to August 27th, 2008. 

 ○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
< Reports from August 21 to August 27, 2008 >
Reports from August 21 to August 27, 2008
○ Other Findings Nothing to disclose this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                                 (PDF 42.2KB)