Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of July 24th)
We are announcing the status of major inspections and restoration works and 
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the 
Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status

 ○ Inspection and restoration completed between July 18th to July 24th, 2008 
    (Completed on the following date) 

  • Unit No.1 Inspection of reactor recirculation piping applicable to the 
    Fitness-for-Service rule: 
     To be completed on July 24th 
  • Unit No.2 500kV power cable inspection (Removal of cables): 
     July 18th 
  • Unit No.3 Core shroud inspection and preventive maintenance (Preventive 
    maintenance): 
     July 18th 
  • Unit No.3 Stack inspection (Detailed inspection for top of stack): 
     To be completed on July 24th 
  • Unit No.4 Excitation transformer inspection (Internal inspection): 
     July 23rd 

 ○ Inspection and restoration to be commenced between July 25th to July 31st, 2008 
    (To be commenced on the following date) 

  • Unit No.1 Stack inspection (Unit No. 1 and No. 2) (Internal inspection 
    of stack): 
     July 28th
  • Unit No.3 Main exhaust duct inspection and restoration (Preparation for 
    restoration work): 
     July 23rd*
  • Unit No.4 House transformer inspection (4B) (Preparation for transportation 
    into the factory): 
     July 22nd*
  • Unit No.4 Excitation transformer inspection (Preparation for transportation 
    into the factory): 
     July 24th*
  • On-site check, inspection and restoration of the oil protection bank for the 
    transformer (Unit No.1 Recovery of oil-contaminated soil): 
     July 29th 
  • Inspection of spent fuel transportation cask storage facility (Inspection for 
    substructure of piles): 
     July 25th 
                                                    * Work schedules added this week.


 ○ Work Schedule of Major Inspection/Restoration from July 20th to August 16th, 2008

  • Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
   Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                          ....Appendix


 (Reference) 
  Nonconformances Found in the Inspection and Restoration Works Performed after the 
  Niigata-Chuetsu-Oki Earthquake

  Based on the "Public Announcement Regarding Nonconformance Found in the Inspection 
  and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo 
  Electric Power Company, Incorporated (TEPCO) provides this announcement containing 
  incidents information reported from July 17th to July 23rd, 2008. 

 ○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
< Reports from July 17 to July 23, 2008 >
Reports from July 17 to July 23, 2008
○ Other Findings • Unit No.6 Visual inspection was conducted for forks of 260 rotor blades on the 16th stage of the low-pressure turbine (C) (130 blades each on generator-side and turbine-side). As a result, no damage was found. Additionally, non-destructive investigation resulted in indications on the forks of 4 rotor blades on the turbine-side. Indication was not found on the generator-side. • While confirming contamination of damaged pallets in the solid waste storage warehouse to have them stored on site, a minuscule amount of radioactive material -- about 1.4 Becquerel/cm2 -- was found on one of the pallets on July 17, 2008. The pallet has been covered by a sheet and is stored in the solid waste storage warehouse.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                                (PDF 46.8KB)