We are announcing the status of major inspections and restoration works and
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the
Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
○ Inspection and restoration completed between July 11th to July 17th, 2008
(Completed on the following date)
Unit No.3 Core shroud inspection and preventive maintenance (Core shroud inspection):
July 4th*
Unit No.3 500kV power cable inspection (Removal of cables):
July 17th
Unit No.3 Stack inspection (Internal inspection of stack):
July 15th
Unit No.4 Inspection of new fuel storage warehouse and new fuels in the warehouse
(Inspection of new fuel storage warehouse):
July 14th
Unit No.4 House transformer inspection (4A Internal inspection):
July 9th*
Unit No.4 House transformer inspection (4B Internal inspection):
July 16th
Unit No.5 Inspection of new fuel storage warehouse and new fuels in the warehouse
(Inspection of new fuels):
July 15th
Restoration work for filtrate tank No.3 and No.4 (No.3 Water leakage test):
July 17th
○ Inspection and restoration to be commenced between July 18th to July 24th, 2008
(To be commenced on the following date)
Unit No.4 House transformer inspection (4B Transportation into the factory):
July 17th*
On-site check, inspection and restoration of the oil protection bank for the
transformer (Unit No.3 Restoration work):
July 21st
On-site check, inspection and restoration of the oil protection bank for the
transformer (Unit No.1 Recovery of oil-contaminated soil):
July 22nd
* Work schedules added this week.
○ Work Schedule of Major Inspection/Restoration from July 13th to August 9th, 2008
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the
Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from July 10th to July 16th, 2008.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
< Reports from July 10 to July 16, 2008 >
|
○ Other Findings
Nothing to disclose this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 43.2KB)
|