We are announcing the status of major inspections and restoration works and
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after
the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
○ Inspection and restoration completed between July 4th to July 10th, 2008
(Completed on the following date)
Unit No.1 Main transformer inspection (On-site transportation):
To be completed on July 10th
Unit No.1 House transformers inspection (1A and 1B On-site transportation):
July 9th
Unit No.1 Stack inspection (Unit No. 1 and Unit No. 2) (Inspection for substructure
of piles):
July 7th
Unit No.2 Inspection of new fuel storage warehouse and new fuels in the warehouse
(Inspection of new fuels):
To be completed on July 10th
Unit No.4 Fuel and control rod inspection (visual inspection of fuels):
July 3rd*
Unit No.5 Inspection of new fuel storage warehouse and new fuels in the warehouse
(Inspection of new fuel storage warehouse):
July 7th
Unit No.5 Stack inspection (Internal inspection of stack):
July 2nd*
Unit No.6 Discharge canal inspection and restoration (Internal inspection of
discharge canal and restoration work):
June 26th*
○ Inspection and restoration to be commenced between July 11th to July 17th, 2008
(To be commenced on the following date)
Unit No.1 500kV power cable inspection (Removal of cables):
July 7th*
Unit No.3 Reactor recirculation piping preventive maintenance (Preparation work):
July 14th
Unit No.3 Stack inspection (Internal inspection of stack):
July 14th
Unit No.4 Inspection of new fuel storage warehouse and new fuels in the warehouse
(Inspection of new fuel storage warehouse):
July 14th
Unit No.4 Inspection of new fuel storage warehouse and new fuels in the warehouse
(Inspection of new fuels):
July 15th
Unit No.4 500kV power cable inspection (Removal of cables):
July 10th*
Unit No.7 Main generator inspection (Restoration work):
July 14th
Unit No.7 Seismic reinforcement works such as pipe supports (Reinforcement works
for the roof truss of the reactor building):
July 14th
On-site check, inspection and restoration of the oil protection bank for the
transformer (Unit No.2 Recovery of oil-contaminated soil):
July 11th
Restoration work for filtrate tank No.3 and No.4 (No.3 Water leakage test):
July 16th
* Work schedules added this week.
○ Work Schedule of Major Inspection/Restoration from July 6th to August 2nd, 2008
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the
Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from July 3rd to July 9th, 2008.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
< Reports from July 3 to July 9, 2008 >
|
○ Other Findings
Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake;
Grades As, A, B, C, D; and non-graded)
| |
* Numbers were corrected to reflect an addition of a nonconformance incident.
Unit No.3
The casing for the low-pressure turbine (C) has been opened and internal inspection
of the turbine has been conducted since June 30, 2008.
On July 4, wears with a maximum length of about 2mm have been found on the tip of
rotor blades (from stages 9 to 11 of the shroud). Wears with a maximum length of
about 1mm have been found on stators, presumably caused by impact with rotors.
The location and size of wear of rotors and stators that were found this time are
similar to those confirmed in low-pressure turbine (A) and (B).
Wears on rotors and stators will be repaired. If similar wears were to be found in
other units, we will notify the fact through this weekly report.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 43.1KB)
|