Press Release (Jul 10,2008)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of July 10th)
We are announcing the status of major inspections and restoration works and 
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after 
the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status

 ○ Inspection and restoration completed between July 4th to July 10th, 2008 
    (Completed on the following date) 

   • Unit No.1 Main transformer inspection (On-site transportation): 
      To be completed on July 10th 
   • Unit No.1 House transformers inspection (1A and 1B On-site transportation): 
      July 9th 
   • Unit No.1 Stack inspection (Unit No. 1 and Unit No. 2) (Inspection for substructure 
     of piles): 
      July 7th 
   • Unit No.2 Inspection of new fuel storage warehouse and new fuels in the warehouse 
     (Inspection of new fuels): 
      To be completed on July 10th 
   • Unit No.4 Fuel and control rod inspection (visual inspection of fuels): 
      July 3rd*
   • Unit No.5 Inspection of new fuel storage warehouse and new fuels in the warehouse 
     (Inspection of new fuel storage warehouse): 
      July 7th 
   • Unit No.5 Stack inspection (Internal inspection of stack): 
      July 2nd*
   • Unit No.6 Discharge canal inspection and restoration (Internal inspection of 
     discharge canal and restoration work):
      June 26th*

 ○ Inspection and restoration to be commenced between July 11th to July 17th, 2008 
    (To be commenced on the following date) 

   • Unit No.1 500kV power cable inspection (Removal of cables): 
      July 7th*
   • Unit No.3 Reactor recirculation piping preventive maintenance (Preparation work): 
      July 14th 
   • Unit No.3 Stack inspection (Internal inspection of stack): 
      July 14th 
   • Unit No.4 Inspection of new fuel storage warehouse and new fuels in the warehouse 
     (Inspection of new fuel storage warehouse): 
      July 14th 
   • Unit No.4 Inspection of new fuel storage warehouse and new fuels in the warehouse 
     (Inspection of new fuels): 
      July 15th
   • Unit No.4 500kV power cable inspection (Removal of cables): 
      July 10th* 
   • Unit No.7 Main generator inspection (Restoration work): 
      July 14th 
   • Unit No.7 Seismic reinforcement works such as pipe supports (Reinforcement works 
     for the roof truss of the reactor building): 
      July 14th 
   • On-site check, inspection and restoration of the oil protection bank for the 
     transformer (Unit No.2 Recovery of oil-contaminated soil): 
      July 11th 
   • Restoration work for filtrate tank No.3 and No.4 (No.3 Water leakage test): 
      July 16th 
                                                       * Work schedules added this week.

 ○ Work Schedule of Major Inspection/Restoration from July 6th to August 2nd, 2008

   • Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                           ....Appendix

 (Reference) 
  Nonconformances Found in the Inspection and Restoration Works Performed after the 
  Niigata-Chuetsu-Oki Earthquake

  Based on the "Public Announcement Regarding Nonconformance Found in the Inspection 
  and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo 
  Electric Power Company, Incorporated (TEPCO) provides this announcement containing 
  incidents information reported from July 3rd to July 9th, 2008. 

 ○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
< Reports from July 3 to July 9, 2008 >
Reports from July 3 to July 9, 2008
○ Other Findings • Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake; Grades As, A, B, C, D; and non-graded)
* Numbers were corrected to reflect an addition of a nonconformance incident. • Unit No.3 The casing for the low-pressure turbine (C) has been opened and internal inspection of the turbine has been conducted since June 30, 2008. On July 4, wears with a maximum length of about 2mm have been found on the tip of rotor blades (from stages 9 to 11 of the shroud). Wears with a maximum length of about 1mm have been found on stators, presumably caused by impact with rotors. The location and size of wear of rotors and stators that were found this time are similar to those confirmed in low-pressure turbine (A) and (B). Wears on rotors and stators will be repaired. If similar wears were to be found in other units, we will notify the fact through this weekly report.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                                 (PDF 43.1KB)