We are announcing the status of major inspections and restoration works and
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after
the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
○ Inspection and restoration completed between June 13th to June 19th, 2008
(Completed on the following date)
Unit No.1 Excitation transformers inspection (transportation into the factory):
June 17th
Unit No.3 Stack inspection (inspection for substructure of piles):
June 10th*
Unit No.6 Stack inspection (detailed inspection for top of stack):
June 16th
Inspection of spent fuel transportation cask:
June 13th
○ Inspection and restoration to be commenced between June 20th to June 26th, 2008
(To be commenced on the following date)
Unit No.2 Core shroud inspection:
June 24th
Unit No.3 Turbine inspection (detailed inspection for high-pressure turbine and
low-pressure turbine (A)):
June 25th
Unit No.3 Turbine inspection (restoration work for blades of low-pressure turbine
(A) and (B)):
June 25th
Unit No.3 500kV power cable inspection (removal of cables):
June 23rd
Unit No.3 Stack inspection (detailed inspection for top of stack):
June 16th*
Unit No.5 Stack inspection (inspection for substructure of piles):
June 20th
Unit No.7 Seismic reinforcement works such as pipe supports (reinforcement works
for pipes):
June 16th*
On-site check, inspection and restoration of the oil protection bank for the
transformer (Unit No.1 preparation for restoration work):
June 23rd
On-site check, inspection and restoration of the oil protection bank for the
transformer (Unit No.6 restoration work):
June 24th
Construction of seismic-isolated essential buildings (site preparation work):
June 23rd
*Work schedules added this week.
○ Work Schedule of Major Inspection/Restoration from June 15th to July 12th, 2008
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the
Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from June 12th to June 18th, 2008.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
< Reports from June 12 to June 18, 2008 >
|
○ Other Findings
Unit No.7
Leak-rate test of the containment vessel was conducted from June 11th to June 12th
to confirm its leak-tightness. The test showed no abnormality.
Unit No.6
Visual inspection was conducted for forks of 252 rotor blades on the 15th stage
and 260 rotor blades on the 16th stage of the low-pressure turbine (B) (15th stage:
126 blades each on generator-side and turbine-side; 16th stage: 130 blades each on
generator-side and turbine-side). As a result, no damage was found. Additionally,
non-destructive investigation resulted in an indication on the fork of a rotor blade
on the turbine-side of 16th stage. Indication was not found on generator-side and
turbine-side of 15th stage and the generator-side of 16th stage.
Unit No.7
Visual inspection was conducted for forks of 260 rotor blades on the 16th stage of
the low-pressure turbine (C) (130 blades each on generator-side and turbine-side).
As a result, no damage was found. Additionally, non-destructive investigation
resulted in indications on the forks of 31 rotor blades on the generator-side and
9 rotor blades on the turbine-side.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 96.4KB)
|