We are announcing the status of major inspections and restoration works and
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after
the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
○ Inspection and restoration completed between June 6th to June 12th, 2008
(Completed on the following date)
Unit No.1 Inspection of new fuel storage warehouse and new fuels in the warehouse
(inspection of new fuels):
June 9th
Unit No.1 Main exhaust duct inspection and restoration (survey prior to restoration work):
June 6th
Unit No.2 Main exhaust duct inspection and restoration (survey prior to restoration work):
June 6th
Unit No.3 Main transformer inspection (transportation into the factory):
June 6th
Unit No.4 Main generator inspection (rotor transportation into the factory):
June 11th
Unit No.6 Inspection of new fuel storage warehouse and new fuels in the warehouse
(inspection of new fuels):
June 9th
Unit No.7 Reactor internal pump input transformer inspection (Electrical testing):
June 7th
Unit No.7 Discharge canal inspection and restoration (internal inspection and restoration
work of discharge canal):
June 7th
○ Inspection and restoration to be commenced between June 13th to June 19th, 2008
(To be commenced on the following date)
Unit No.1 Inspection of reactor recirculation piping applicable to the
Fitness-for-Service rule:
June 16th
Unit No.1 House transformers inspection (preparation for on-site transportation):
June 14th
Unit No.1 Excitation transformers inspection (transportation into the factory):
June 17th
Unit No.1 Stack inspection (internal inspection):
June 16th
Unit No.3 Circulating water pipe inspection
(foundation improvement, excavating work, and inspection of pipes):
June 16th
Unit No.4 Fuel and control rod inspection (visual inspection of fuels):
June 17th
Unit No.4 Turbine inspection (detailed inspection for low-pressure turbine (B) and (C)):
June 19th
Unit No.4 House transformers inspection (4A and 4B) (preparation for inspection):
June 16th
Unit No.4 Excitation transformers inspection (preparation for inspection):
June 16th
Unit No.7 Discharge canal inspection and restoration (removal of bypass pipe):
June 18th
○ Work Schedule of Major Inspection/Restoration from June 8th to July 5th, 2008
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear Power
Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed
after the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from June 5th to June 11th, 2008.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
< Reports from June 5 to June 11, 2008 >
|
○ Other Findings
Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake;
Grades As, A, B, C, D; and non-graded)
| |
Unit No.7
As part of safety integrity verification of the reactor pressure vessel, pressure/leakage
test was conducted on June 3, 2008 by increasing the pressure to about 3.5 MPa-half of that
during normal operation. The test showed no abnormality. Leak-rate test of the containment
vessel will be conducted from June 11 to confirm its leak-tightness.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
(PDF 97.9KB)
|