Press Release (Jun 12,2008)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of June 12th)
We are announcing the status of major inspections and restoration works and 
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after 
the Niigata-Chuetsu-Oki Earthquake.  

Inspection/Restoration Status

 ○ Inspection and restoration completed between June 6th to June 12th, 2008  
    (Completed on the following date) 

   • Unit No.1 Inspection of new fuel storage warehouse and new fuels in the warehouse 
     (inspection of new fuels): 
        June 9th 
   • Unit No.1 Main exhaust duct inspection and restoration (survey prior to restoration work):
        June 6th 
   • Unit No.2 Main exhaust duct inspection and restoration (survey prior to restoration work):
        June 6th 
   • Unit No.3 Main transformer inspection (transportation into the factory): 
        June 6th 
   • Unit No.4 Main generator inspection (rotor transportation into the factory): 
        June 11th 
   • Unit No.6 Inspection of new fuel storage warehouse and new fuels in the warehouse 
     (inspection of new fuels): 
        June 9th 
   • Unit No.7 Reactor internal pump input transformer inspection (Electrical testing): 
        June 7th 
   • Unit No.7 Discharge canal inspection and restoration (internal inspection and restoration 
     work of discharge canal): 
        June 7th 

 ○ Inspection and restoration to be commenced between June 13th to June 19th, 2008  
    (To be commenced on the following date)  

   • Unit No.1 Inspection of reactor recirculation piping applicable to the 
     Fitness-for-Service rule: 
        June 16th 
   • Unit No.1 House transformers inspection (preparation for on-site transportation): 
        June 14th 
   • Unit No.1 Excitation transformers inspection (transportation into the factory): 
        June 17th 
   • Unit No.1 Stack inspection (internal inspection): 
        June 16th 
   • Unit No.3 Circulating water pipe inspection 
     (foundation improvement, excavating work, and inspection of pipes): 
        June 16th 
   • Unit No.4 Fuel and control rod inspection (visual inspection of fuels): 
        June 17th 
   • Unit No.4 Turbine inspection (detailed inspection for low-pressure turbine (B) and (C)): 
        June 19th 
   • Unit No.4 House transformers inspection (4A and 4B) (preparation for inspection): 
        June 16th 
   • Unit No.4 Excitation transformers inspection (preparation for inspection): 
        June 16th
   • Unit No.7 Discharge canal inspection and restoration (removal of bypass pipe): 
        June 18th

 ○ Work Schedule of Major Inspection/Restoration from June 8th to July 5th, 2008

   •Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear Power 
     Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                                    ....Appendix

 (Reference) 
  Nonconformances Found in the Inspection and Restoration Works Performed 
  after the Niigata-Chuetsu-Oki Earthquake

  Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and 
  Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric 
  Power Company, Incorporated (TEPCO) provides this announcement containing incidents 
  information reported from June 5th to June 11th, 2008.  

 ○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
< Reports from June 5 to June 11, 2008 >
Reports from June 5 to June 11, 2008
○ Other Findings • Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake; Grades As, A, B, C, D; and non-graded)
• Unit No.7 As part of safety integrity verification of the reactor pressure vessel, pressure/leakage test was conducted on June 3, 2008 by increasing the pressure to about 3.5 MPa-half of that during normal operation. The test showed no abnormality. Leak-rate test of the containment vessel will be conducted from June 11 to confirm its leak-tightness.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear