We are announcing the status of major inspections and restoration works and
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after
the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
○ Inspection and restoration completed between May 30th to June 5th, 2008
(Completed on the following date)
• Unit No.1 Fuel and control rod inspection (visual inspection of fuels):
May 30th
• Unit No.1 Fuel and control rod inspection (visual inspection of channel box):
May 30th
• Unit No.2 Main transformer inspection (on-site transportation):
June 3rd
• Unit No.3 Main transformer inspection (preparation for transportation into the factory):
June 4th
• Unit No.3 Main transformer inspection (on-site transportation):
To be completed on June 5th
• Unit No.3 Main exhaust duct inspection and restoration (survey prior to restoration work):
May 30th
• Unit No.4 Stack inspection (detailed inspection for top of stack):
May 28th*
• Unit No.5 Main exhaust duct inspection and restoration (survey prior to restoration work):
May 30th
• Restoration work for filtrate tank #3 and #4 (#4 restoration work):
June 2nd
○ Inspection and restoration to be commenced between June 6th to June 12th, 2008
(To be commenced on the following date)
• Unit No.1 and 2 Stack inspection (detailed inspection for top of stack):
June 9th
• Unit No.3 Core shroud inspection and preventive maintenance (preventive maintenance):
June 11th
• Unit No.3 Main transformer inspection (transportation into the factory):
June 6th
• Unit No.4 Main generator inspection (rotor transportation into the factory):
June 11th
• On-site check, inspection and restoration of the oil protection bank for
the transformer (Unit No.5 preparation work for restoration):
June 3rd*
*Work schedules added this week.
○ Work Schedule of Major Inspection/Restoration from June 1st to June 28th, 2008
• Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear Power
Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the
Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from May 29th to June 4th, 2008.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake) |
< Reports from May 29 to June 4, 2008 > |
○ Other Findings
• Unit No.6
Visual inspection and non-destructive inspection for forks of rotor blades on the
14th stage of the low-pressure turbine (A), (B) and (C) and forks of rotor blades
on the 15th and 16th stage of the low-pressure turbine (B) are going on (announced
on May 15th, 2008).
Visual inspection was conducted for forks of 304 rotor blades on the 14th stage of
the low-pressure turbine (B) (152 blades each on generator-side and turbine-side).
As a result, no damage was found. Additionally, non-destructive investigation
resulted in indications in the forks of 28 rotor blades on the generator-side and
63 rotor blades on the turbine-side.
Subsequently, investigation on the cause of the damages and indications will be
continued as well as visual and non-destructive inspection for forks of rotor blades
on the 14th stage of the low-pressure turbine (A) and (C) and forks of rotor blades
on the 15th and 16th stages of the low-pressure turbine (B), and non-destructive
inspection for fixtures of rotor fork of the 14th stage of low-pressure turbine. Appendix: Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 179KB) |