We are announcing the status of major inspections and restoration works and
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after
the Niigata-Chuetsu-Oki Earthquake.
1. Inspection/Restoration Status
○ Inspection and restoration completed between April 18th to April 24th, 2008.
(Completed on the following date)
Unit No.4 Fuel and control rod inspection (visual inspection of channel box):
April 21st
Unit No.4 Fuel and control rod inspection (visual inspection of control rod):
April 21st
Unit No.5 Main generator inspection (rotor carrying in):
April 24th
○ Inspection and restoration to be commenced between April 25th to May 8th, 2008
(To be commenced on the following date)
Unit No.1 Fuel and control rod inspection (visual inspection of channel box):
April 23rd*
Unit No.2 Main transformer inspection (on-site transportation):
May 5th
Unit No.3 Inspection of reactor recirculation piping applicable to the
Fitness-for-Service rule (detailed inspection):
May 7th
Unit No.3 Turbine inspection (low pressure turbine (B) (C) detailed inspection):
May 7th
Unit No.4 Stack inspection (detailed inspection for top of stack):
May 7th
Unit No.5 House transformers (5A) inspection (on-site transportation):
April 28th
Unit No.5 Excitation transformers inspection (on-site transportation):
April 28th
Unit No.6 Main transformer inspection (carrying in and installation work):
April 25th
On-site check/inspection/restoration of the oil protection bank for the transformer
(Unit No.3 Recovery of oil-contaminated soil):
May 7th
Restoration and reinforcement work for on-site and outside roads, slope, etc.
(preparation work for reinforcement):
April 25th
*Work schedules added this week.
○ Work Schedule of Major Inspection/Restoration from April 20th to May 17th, 2008
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
2. Nonconformances Found in the Inspection and Restoration Works Performed
after the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from April 17th to April 23rd, 2008.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
<Reports from Apr. 17 to Apr. 23, 2008>
|
○ Other Findings
Nothing to disclose this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 103KB)
|