We are announcing the status of major inspections and restoration works and
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after
the Niigata-Chuetsu-Oki Earthquake.
1. Inspection/Restoration Status
○ Inspection and restoration completed between February 29th to March 6th, 2008.
(Completed on the following date)
Unit No.1 Pressure suppression chamber inspection:
March 1st
Unit No.1 Fuel and control rod inspection (spent fuel pool rack, etc.):
February 29th
Unit No.1 Main generator inspection (withdrawal of rotor):
March 5th
Unit No.5 Jet pump inspection (No.1 disassembly):
February 28th*
Unit No.5 House transformer (5B) internal inspection:
March 3rd
Unit No.6 Pressure suppression chamber inspection:
March 6th
* Work schedules added this week
○ Inspection and restoration to be commenced between March 7th to March 13th, 2008
(To be commenced on the following date)
Unit No.2 Pressure suppression chamber inspection (preparation):
March 12th
Unit No.3 Fuel and control rod inspection (spent fuel pool rack, etc.):
March 10th
Unit No.3 Excitation transformers inspection (preparation for transportation
into the factory):
March 12th
Unit No.5 Preparation for excitation transformers inspection (oil extraction
and internal inspection):
March 10th
Unit No.6 Main generator inspection:
March 10th
Unit No.6 Discharge canal inspection and restoration (maintenance work):
March 10th
Unit No.6 Stack inspection (detailed inspection for top of stack):
March 10th
Unit No.7 Main transformer inspection (preparation for carrying in):
March 10th
Unit No.7 500 kV power cable (OF cable) inspection (energization for testing
without load):
March 8th
Unit No.7 Discharge canal inspection and restoration (maintenance work):
March 10th
Outdoor fire protection system piping to be placed above ground, installation
of fire protection tank, etc. (replacement of onsite panel of foam fire
extinguisher):
March 10th
Restoration work for port facility (wharf):
March 10th
○ Work Schedule of Major Inspection/Restoration from March 2nd to March 29th,
2008
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa
Nuclear Power Station in Response to the Niigata-Chuetsu-Oki Earthquake
(during 4 Weeks) ....Appendix
2. Nonconformances Found in the Inspection and Restoration Works Performed after
the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from February 28th to March 5th, 2008.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
<Reports from Feb. 28 to Mar. 5, 2008>
|
○ Other Findings
Nothing to disclose this week
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 204KB)
|