We are announcing the status of major inspections and restoration works and
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after
the Niigata-Chuetsu-Oki Earthquake.
1. Inspection/Restoration Status
○ Inspection and restoration completed between February 8th to February 14th, 2008.
(Completed on the following date)
Unit No.2 Fuel and control rod inspection (fuel):
February 1st *
Unit No.2 Fuel and control rod inspection (channel box):
February 12th
Unit No.3 Inspection of reactor recirculation piping applicable to
the Fitness-for-Service rule (ultrasonic testing):
February 13th
Unit No.6 Replacement of seismic data recorders:
February 8th
* Work schedules added this week
○ Inspection and restoration to be commenced between February 15th to February 21st,
2008
(To be commenced on the following date)
Unit No.1 Fuel and control rod inspection (control rod):
February 15th
Unit No.3 House transformer inspection (preparation for transportation into
the factory):
February 20th
Unit No.3 Main generator inspection:
February 18th
○ Work Schedule of Major Inspection/Restoration from February 10th to March 8th, 2008
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
2. Nonconformances Found in the Inspection and Restoration Works Performed after
the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from February 7th to February 13th, 2008.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
<Reports from Feb. 7 to Feb. 13, 2008>
|
○ Other Findings
Unit No.7:
Root cause analysis has been conducted for the 2 minor cracks (length of about 3mm
and 2mm) found on the reactor well liner.
The location of cracks has been identified to be on the welded portion of the liner.
Insufficient welding was found due to locational difficulty caused by the structure
as well as liner thinning caused by grinding process to remove excess weld.
It is assumed that due to the earthquake, the welded portion was hit by a slot plug,
leading to penetration cracks.
The portion of liner that was cut out for root cause analysis will be repaired by
welding by February 26th. Leakage will be confirmed at the next occasion of reactor
well fill-up.
Unit No.3:
Ultrasonic testing was conducted from January 22nd to February 13th for the crack
found on the PLR pipe joint that had been found during the previous inspection.
No new crack was found on the joint. Depth of the crack will be determined through
cross-sectional observation. Prepare work will be done for cutting the pipe.
Solid waste storage warehouse:
20,027 drums have been confirmed as of January 31st, 2008.
Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake;
Grades As, A, B, C, D; and non-graded)
|
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 176KB)
|