We are announcing the status of major inspections and restoration works and
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after
the Niigata-Chuetsu-Oki Earthquake.
1. Inspection/Restoration Status
○ Inspection and restoration completed between January 25th to January 31st, 2008.
(Completed on the following date)
Unit No.6 In-core inspection (Phase3):
January 28th
○ Inspection and restoration to be commenced between February 1st to February 7th, 2008
(To be commenced on the following date)
Unit No.1 Fuel/control rod inspection (control rod racks):
February 4th
Unit No.3 Preparation for in-core inspection (Phase3):
February 1st
Unit No.3 In-core inspection (Phase3):
February 6th
Unit No.6 Fuel/control rod inspection:
February 1st
Pre-construction geological survey for seismic-isolated essential buildings:
February 4th
Inspection of spent fuel transportation cask:
February 5th
○ Work Schedule of Major Inspection/Restoration from January 27th to February 23rd, 2008
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
2. Nonconformances Found in the Inspection and Restoration Works Performed after
the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from January 24th to January 30th, 2008.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
<Reports from Jan. 24 to Jan. 30, 2008>
|
○ Other Findings
Nothing to disclose this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 164KB)
|