As for the Unit 1, the in-core inspections (Phase 3) which started on
Nov. 26th, finished today.
Hereby, all of the unit 1 in-core inspections(Phase 1,2 and 3) which
started on Aug. 1st, have been completed.
○ Period
From Nov. 26th, 2007 to Dec. 14th, 2007
○ Area
control rod guide tube, neutron flux monitor guide tube, neutron flux
monitor guide tube stabilizer, neutron flux monitor housing, control
rod drive mechanism housing, shroud support core support plate, core
shroud .
○ Result
No abnormality such as damage, deformation and dropout has been found.
|