Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (December 13th)
We are announcing the status of major inspections and restoration works and 
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after 
the Niigata-Chuetsu-Oki Earthquake.  

1. Inspection/Restoration Status

 ○ Inspection and restoration completed between December 7th to December 13th, 2007
    (Completed on the following date)
  • Unit No.2 In-core inspection (control rod storage hangers in the spent fuel pool):
       December 8th 
  • Unit No.4 Refueling machine inspection: 
       December 10th 
  • Unit No.4 In-core inspection (control rod storage rack and hangers in the spent 
    fuel pool):
       December 12th 
  • Unit No.4 Reactor head opening:
       December 10th 
  • Unit No.4 Main transformer oil extraction and internal inspection:
       December 13th 
  • Unit No.4 House transformers inspection (transportation into the factory):
       December 6th*

                                                      *Work schedules added this week

 ○ Inspection and restoration to be commenced between December 7th to December 13h,
    2007
    (To be commenced on the following date)
  • Unit No.2 Reactor pressure vessel inspection (nozzle parts etc.):
       December 14th 
  • Unit No.4 Main transformer inspection (preparation for transportation into 
    the factory)
       December 14th 
  • Unit No.5 Reactor pressure vessel inspection (nozzle parts etc.):
       December 14th 
  • Unit No.7 Restoration work for oil protection bank for the transformer:
       December 17th 

 ○ Work Schedule for Major Inspection/Restoration from December 9th, 2007 to January 
    5th, 2008
  • Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa 
    Nuclear Power Station in Response to the Niigata-Chuetsu-Oki Earthquake 
    (during 4 Weeks)....Appendix

2. Nonconformances Found in the Inspection and Restoration Works Performed after 
   the Niigata-Chuetsu-Oki Earthquake

   Based on the "Public Announcement Regarding Nonconformance Found in the Inspection 
   and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", 
   the Tokyo Electric Power Company, Incorporated (TEPCO) provides this announcement 
   containing incidents information reported from December 6th to December 12th, 2007.

 ○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
<Reports from Dec. 6 to Dec. 12, 2007>
Reports from Dec. 6 to Dec. 12, 2007
○ Other Findings • Solid Waste Storage Facility: Number of drums conducted the soundness verification work: 12,718 (as of November, 30th) • Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake; Grades As, A, B, C, D; and non-graded)
Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake; 
 Grades As, A, B, C, D; and non-graded)
Appendix: Work Schedule of the Main Inspection/Restoration of Kashiwazaki-Kariwa Nuclear 
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake
          (during 4 Weeks)(PDF 222KB)