We are announcing the status of major inspections and restoration works and
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after
the Niigata-Chuetsu-Oki Earthquake.
1. Inspection/Restoration Status
○ Inspection and restoration completed between November 30th to December 6th, 2007
(Completed on the following date)
Unit No.1 Turbine inspection (internal inspection):
November 30th
Unit No.2 Excitation transformers oil extraction and internal inspection:
December 3rd
Unit No.3 Removal of spent fuel pool underwater work platform:
December 4th
Unit No.4 Refueling floor service tools inspection (stud tensioners, etc.)
December 3rd
Unit No.4 Removal of spent fuel pool underwater work platform:
December 5th
Unit No.5 In-core inspection (Phase1 and Phase2):
December 6th
Unit No.6 Reactor internal pump input transformer transportation into the factory:
December 3rd
Unit No.7 In-core inspection (Phase1 and Phase2):
November 30th
Unit No.7 Turbine inspection (internal inspection):
November 30th
Inspections of house boilers (Arahama-side)
November 30th
○ Inspection and restoration to be commenced between December 7th to December 13h, 2007
(To be commenced on the following date)
Unit No.2 In-core inspection (spent fuel pool rack hangers):
December 7th
Unit No.4 In-core inspection:
December 11th
Unit No.4 Reactor pressure vessel inspection (nozzle parts etc.):
December 8th
Unit No.4 Main transformer oil extraction and internal inspection:
December 11th
Unit No.5 In-core inspection (Phase3):
December 13th
Unit No.7 In-core inspection (Phase3):
December 10th
Replacement of seismic data recorders (Unit No.1, 5 and 6):
December 10th
○ Work Schedule for Major Inspection/Restoration from December 2nd to December 29th, 2007
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear Power
Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)....Appendix
2. Nonconformances Found in the Inspection and Restoration Works Performed after
the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake",
the Tokyo Electric Power Company, Incorporated (TEPCO) provides this announcement
containing incidents information reported from November 30th to December 5th, 2007.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
<Reports from Nov. 30 to Dec. 5, 2007>
|
○ Other Findings
Unit No.3:
As a result of visual inspections of the spent fuel pool conducted subsequent to
the removal of underwater work platform in the pool (completed on December 3rd),
two minor scratches were found on the spent fuel pool wall (completed on December 4th).
Unit No.4:
As a result of visual inspections of the spent fuel pool conducted subsequent to
the removal of underwater work platform in the pool (completed on November 30th),
four minor scratches on the spent fuel pool wall and a minor scratch on the handle
of the fuel assembly were found (completed on December 5th).
Unit No.6:
The two control rods that could not be pulled out initially were disassembled and
inspected to measure the labyrinth seal and the ratch mechanism. However, no
abnormality (such as foreign material or a large damage) was found. No abnormality
(such as scratch, deformation, etc.) was found for equipment on the reactor-side
(control rod, fuel support, fuel guide) as well. We will continue to investigate
the cause.
Unit No.7:
As a result of the detailed inspection of the low-pressure turbine (B), wears
(maximum about 2mm) were found at the edges of the rotor blades (shrouds of the 10th
to 12th stage). These wears are presumed to have happened due to contact of the rotor
blades and the stator blades. A wear (maximum about 1mm) was also found at the stator
blade. Repair works will be considered.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake
(during 4 Weeks)(PDF 207KB)
|