We are announcing the status of major inspections and restoration works (from
September 2nd to 29th, 2007) and non-conformance at TEPCO's Kashiwazaki-Kariwa
Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
1. Inspection/Restoration Status
○Inspection and restoration completed between August 24th to September 6th, 2007
Unit No.1 Main transformers inspection: Visual inspection completed on August
29th.
Unit No.2 Turbine building ceiling crane inspection: Inspection completed on
August 24th.
Inspection preparation & restoration for the bushing of Minami-Niigata
transmission line (No.2): Replacement to spare parts completed on August 31st.
Solid Waste Storage Facility Temporary Restoration: Completed on August 31st
(Returning tipped-over drums to their original position).
Verification operation of stand-by equipments of the residual heat removal
system: Completed on August 31st.
Survey for transformer oil leakage area: Completed on September 3rd.
Unit No.1 House transformers (1A) Inner inspection: Completed on September
4th.
Unit No.3 House transformers (3A) Visual inspection: Completed on September
4th.
Unit No.7 Reactor building ceiling crane inspection: To be completed on
September 6th.
Repair/restoration of low-voltage start-up transformer 6SB: To be completed
on September 6th.
○Inspection to be commenced between September 7th to 13th, 2007.
Unit No.1 - 5 Main exhaust ducts inspection preparation
Unit No.7 Refueling floor service tools inspection (working dolly, stud
tensioners, etc.)
Unit No.6 House transformer oil extraction and internal inspection
preparation.
Verification operation of the standby gas treatment system.
Preparation for dismantling the Arahama-side arrestor steel tower.
2. Work Schedule for Major Inspection/Restoration (From September 2nd to September
29th, 2007)
Work Schedule of the Main Inspection/Restoration of Kashiwazaki Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake(during 4 Weeks)
Appendix
"In-core inspection of Kashiwazaki-Kariwa NPS" Attachment
3. Nonconformances Found in the Inspection and Restoration Works Performed after
the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the
Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki
Earthquake", the Tokyo Electric Power Company, Incorporated (TEPCO) provides
this announcement containing incidents information reported from August 23rd to
September 5th, 2007 and the occurrence status of nonconformances (that have
been deliberated) reported from August 16th to 29th, 2007.
|
* The total number of injured persons at the Kashiwazaki-Kariwa site after
the Niigata-Chuetsu-Oki Earthquake (since Aug 10th, 2007) is listed on
"○ Other Findings" mentioned below.
○Information on Nonconformances (those related to: the Chuetsu-Oki
Earthquake; Grades As, A, B, C, and D; and non-graded)
|
○Other Findings
From the survey and analyses of the soil at the crack of the units 4, 5, 7
transformer oil protection bank, insulating oil was found to have infiltrated
into the soil. Incident report regarding leakage of insulating oil of
electrical equipments has been submitted on September 6th in accordance to
the relevant law. Detailed survey of the soil and necessary actions will be
taken accordingly.
Total number of injured persons at the Kashiwazaki-Kariwa site since Aug 10th,
2007: 1 (no radiation exposure)
Appendix: Work Schedule of the Main Inspection/Restoration of Kashiwazaki Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake
(during 4 Weeks)(PDF 217KB)
Attachment: In-core Inspection of Kashiwazaki-Kariwa NPS(PDF 100KB)
|