Based on the "Public Announcement Regarding Nonconformance Found in the
Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki
Earthquake", the Tokyo Electric Power Company, Incorporated (TEPCO) provides
this announcement containing incidents information reported from August 17
to 22, 2007 and the occurrence status of nonconformances (that have been
deliberated) reported from August 9 to 15, 2007.
1. Incidents Information (relating to the Chuetsu-Oki Earthquake)
<Reports from August 17 to 22, 2007>
2. Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake;
Grades As, A, B, C, and D; and non-graded)
3. Work Schedule for Major Inspection/Restoration
Please refer to the Appendix "Work Schedule for Major Inspection/Restoration
of Kashiwazaki-Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (for the upcoming 4 Weeks)"
4. Other Findings
-Incore inspection (Phase1) of Unit 1 was conducted from August 21 to 23
and no abnormality such as damage, deformation, and fallen parts was confirmed.
Appendix
Work Schedule of the Main Inspection/Restoration of Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake(during 4 Weeks)(PDF 720KB)
|