Tokyo --- Tokyo Electric Power Co. (TEPCO) has been checking the
condition and safety of its nuclear power plants since the
announcement last August about inappropriate management in the
safety records of TEPCO's self-imposed inspections.
A subcommittee of an advisory council to the Minister of Economy,
Trade and Industry, which is to assess the condition of the
facilities, has been evaluating cracks that were identified in the
nuclear power plants. The Nuclear and Industrial Safety Agency
(NISA) submitted the interim report to the subcommittee on March 10.
This concerns an assessment of cracks on the shrouds and the pipes
of the primary loop re-circulation system at TEPCO's nuclear power
plants.
Based on the conclusions of NISA's interim report, TEPCO has announced
its basic approach to the maintenance of cracks, which is as follows:
(Cracks on the shrouds)
-The subcommittee concluded that the cracks on the shrouds do not
need to be immediately repaired. However, it is necessary for the
cracks to be examined with appropriate regularity so that any
development in the cracks can be identified.
-Based on this conclusion, TEPCO will remove all cracks except very
small ones and ones that will not affect the condition of the shroud.
(Cracks on the pipes of primary loop re-circulation system)
-TEPCO will remove the cracks on the pipes of the primary loop
re-circulation system by eliminating the cracks or replacing the
pipes, since it will take some time to carry out another assessment
of the condition of the plant, after confirming the reliability of
the examination data obtained through the improved ultrasonic test.
TEPCO will explain its approach to maintenance work, as well as the
results of comprehensive checks on the appropriateness of past
inspections and progress on preventative measures, both to residents
in the vicinity of nuclear power stations, and to all parties involved.