TREATED WATER PORTAL SITE

ABOUT

At the Fukushima Daiichi Nuclear Power Station we are enlisting the cooperation
of a great many people in order to move forward with countermeasures for contaminated water that was generated in conjunction with the accident and contained high concentrations of radioactive substances.
Through this portal site we shall explain the current situation and give you data/information on ALPS treated water, etc. while also showing how we have removed the radioactive substances from contaminated water and reduced risks.

Note on “Water treated with multi-nuclide removal equipment, etc.” is notated. (revised in April, 2021)

Water treated with multi-nuclide removal equipment (ALPS) so that the concentrations of radioactive materials other than tritium sufficiently satisfy regulatory standards for safety (sum of ratios of legally required concentrations, excluding tritium, is less than 1) shall be referred to as, “ALPS treated water.” Water that has been purified with multi-nuclide removal equipment (ALPS), but for which the concentrations of radioactive materials do not meet regulatory standards for safety (sum of ratios of legally required concentrations, excluding tritium, is 1 or higher) shall be referred to as, "Treated water to be re-purified." The term “ALPS treated water, etc.” shall be used when referring collectively to both types of water.

*The terms used in past documents shall remain unedited. Hence, the definitions differ slightly from the terms used after the March 11, 2020 revision of said terms.

information
[an error occurred while processing this directive]

Amount of ALPS treated water, etc. and Sr removed water stored in tanks

  • *Amount of water between the bottom of a tank and the lower measuring limit of the water gauge
[an error occurred while processing this directive]

ALPS treated water, etc.

ALPS treated water %(m³)
Water to be re-purified %(m³)

  • Decimal points have been rounded so the totals for the amount of water in storage may not equal 100.

Sr removed water

tank

%

Storage Amounts and Radioactive Concentration of ALPS treated water, etc.

  • [an error occurred while processing this directive]

    *Only completely filled tanks (including repurposed tanks) were used to calculate the amount, so this amount may differ from the entire amount of stored water.

Sr removed water

tank
chart text

At current time, ALPS treated water, etc. is being stored in tanks after removing most radionuclides, with the exception of tritium. ALPS has the ability to remove radionuclides (with the exception of tritium) to levels below “concentrations required by law,” which is the Japanese government’s regulatory standard used when discharging contaminated water/treated water* into the environment.
However, as a result of malfunctionsthat occurred when the equipment was put into operation and differing operating objectives that have changed with time, the amount of water being stored at current time is as shown in the diagram on the right that breaks down the amounts by the sums of the ratios of the concentrations required by law.

Tanks and Site use

ALPS treated water, etc. is being stored in tanks on site. On December 11, 2020, the construction of tanks with a capacity of approximately 1.37 million m³ was completed. However, the amount stored in tanks is expected to reach the planned capacity by the summer of 2022. (Tank Construction Progress Status)
We have to examine how to utilize the entire site as work progresses in order to construct of facilities needed for decommissioning (tanks for continuous storage, temporary storage facilities for spent fuel and fuel debris, etc.) amidst site space restrictions.

  • Before the earthquake
    November , 2009
  • Immediately following the earthquake
    May, 2011
  • Tank construction over time
    Flanged tanks were constructed between March, 2011 and March, 2013.
  • Tank construction over time
    Welded tanks were constructed between April, 2013 and December, 2014.
  • Tank construction over time
    The replacement of flanged tanks began in January, 2015 and will be completed in December, 2020.
Tank construction plan

*On December 11, 2020, the installation of approximately 1.37 million m3 of tanks was completed.

  • ※1 The rate of increase of ALPS treated water, etc. will slow in conjunction with the anticipated completion of the treatment of Sr removed water stored in welded tanks.
  • ※2 This estimate assumes that contaminated water generation falls to around 150 ㎥ /day during 2020. The estimate was calculated assuming that daily contaminated water generation would fluctuate between 130-170 ㎥ /day due to the impact from groundwater flow into each building and rainfall.
  • ※3 Tanks deemed necessary for treating water with ALPS.

Map of entire site

Current utilization of the Fukushima Daiichi Nuclear Power Station site

※Buildings drawn with a dotted line indicate facilities that will be built in the future
※As of October, 2019

Examination of future site utilization

We have to examine how to utilize the entire site as work progress in order to construct facilities needed for decommissioning.

North side of the site
Area to be utilized for waste treatment and storage
South side of the site
Area to be utilized for “tanks for storing ALPS treated water, etc.” and “temporary storage facilities for spent fuel and fuel debris”, etc.

Facilities to be determined going forward

Contaminated Water Treatment History

The Japanese government’s standard for storing ALPS treated water, etc. at the Fukushima Daiichi Nuclear Power Station stipulates that
“the effective dose at site borders must be under 1mSv/year.”Since FY2013 we have been purifying contaminated water with multi-nuclide removal equipment (ALPS) and as of the end of FY2015 had achieved our goal of reducing the effective dose rate at site borders to below 1mSv/year. After achieving this goal, ALPS continued to be operated with the intention of reducing risks at the power station

FY2013~FY2015

FY2013~FY2015

  • Issues Addressed

    The site border dose rate during 2013, when highly radioactive contaminated water from which only cesium had been removed was being stored in tanks on site, was 9.76mSv/year, thereby greatly exceeding the “effective dose at site borders of 1mSv/year or less,” which was the standard stipulated by the government.

  • Treatment Plan

    The multi-nuclide removal equipment (ALPS) was put into operation in 2013 and equipment operation rate was increased to purify contaminated water and quickly reach the objective of reducing effective dose rates at site borders to below 1 mSv/year.

  • Achievements

    As a result of purifying contaminated water with the ALPS, the effective dose rates at site borders was reduced to below 1 mSv/year by the end of FY2015. However, due to nonconformances with the ALPS equipment, concentrations of radionuclides require by law were exceeded.

    ※1 Percentage of cases where the concentrations required by law were exceeded based on the number of samples and broken down for each radionuclide.
    ※2 Total amount treated by existing ALPS, additionally installed ALPS, high-performance ALPS

Close

FY2016

FY2016

  • Issues Addressed

    The multi-nuclide removal equipment (ALPS) enabled much progress to be made with contaminated water treatment thereby causing the amount of treated water to exceed the storage capacity of constructed tanks and we started to run out of tanks to store treated water.

  • Treatment Plan

    In addition to accelerating the construction of tanks to store the treated water, the purification capacity of ALPS was leveraged and equipment operated while keeping in mind the concentrations required by law for each type of radionuclide.

  • Achievements

    As a result of leveraging ALPS purification capacity, in comparison to FY2013~FY2015, the percentage of cases where the concentrations of radionuclides required by law were exceeded decreased.

    ※1 Percentage of cases where the concentrations required by law were exceeded based on the number of samples and broken down for each radionuclide.
    ※2 Total amount treated by existing ALPS, additionally installed ALPS, high-performance ALPS

Close

FY2017~

フェーズ.3 [2017~]

  • Issues Addressed

    Water being stored in bolt-tightened flanged tanks, which pose a high risk of leaking, will be treated as quickly as possible.

  • Treatment Plan

    All water stored in flanged tanks shall be treated with the multi-nuclide removal equipment (ALPS) by the end of FY2018 while maintaining effective dose rates at site borders at below 1 mSv/year and increasing the operation rate of ALPS in an effort to reduce risk.

  • Achievements

    The operation rate of ALPS was increased while keep in mind the objective of reducing risks associated with water stored in flanged tanks. As a result, while the treatment of all the Sr removed water (water that had yet to be treated with ALPS) stored in flanged tanks was completed in November 2018, the percentage of cases where the concentrations of radionuclides required by law were exceeded increased compared to FY2016.Transfer of all ALPS-treated water stored in bolted flange tanks to welded tanks was completed in March, 2019.

    ※1 Percentage of cases where the concentrations required by law were exceeded based on the number of samples and broken down for each radionuclide.
    ※2 Total amount treated by existing ALPS, additionally installed ALPS, high-performance ALPS

Close

The Future Handling of ALPS treated water, etc.

Q&A

Question and Answer

Let us answer your questions.

    [an error occurred while processing this directive]